- What was the plan?
- What actually happened?
- What went well? So we can be sure to do it again.
- What went wrong? So we can figure out how to do better.
- What are we going to do now?
“Command Center” brings up images of NASA or maybe a natural disaster response team. For a large planned maintenance turnaround the furniture and technology may be different but the concepts are much the same. The command center is the place where the outage leader directs the resources of the turnaround. To do this successfully
Unplanned work is a failure of either planning or reliability engineering:
So, when change happens we celebrate because this is an opportunity to learn and improve That’s a “GT”, as in 10 miles north of Grahamstown South Africa. Milestones were originally stone markers used by Roman road builders as a series of numbered markers provide reference points along the road. They can be used to reassure travelers that the proper path is being followed, and to indicate either distance traveled or the remaining distance to a destination.
Funny story – on Nantucket Island, located off the coast of Cape Cod in Massachusetts, USA the road from town to Siasconset is named the Milestone Road. They have a Pi Milestone at 3.14 miles from town. In a plant maintenance turnaround keeping track of the outage events and issues is a vital way for the organization to learn where they are and where they are going. Its almost impossible to reconstruct the battle after the fact; memories fade, rationalizations creep in. If you aren’t paying attention to the road markers and something happens how do you know where you are? When all you measure is when the shutdown started and when it ended all you know is the total lost production time. When key steps along the way are planned and recorded you can learn where the time goes, and then take steps to attack the biggest deviations. Maintenance outages, turnarounds, or plant shutdowns are complex, and can involve hundreds or even thousands of temporary workers, and are very costly. In our work we have been successful in helping reduce large facility outage durations. The immediate benefits are increased process availability and corresponding revenue and profit. Typical outages are planned and scheduled months in advance and last anywhere from a week to a month or more. Outage duration tactics include streamlining processes such as the shutdown and startup processes, improving the decision making and communications methods, and controlling scope. Another tactic is externalizing tasks, which is by doing work before or after the process goes down, tasks such as pre staging tools and materials, preparing the work site. We’ve also been working to better understand the nature of planning and executing Critical Path work.
We believe that a shorter critical path means an overall shorter outage. To get a shorter critical path you often have to add additional resources which increases turnaround costs. What we want to better understand are the conditions where a shorter outage actually costs less. Typical contractor schedules are 2 ten hour shifts per day. Productivity is believed to drop off significantly after 10 hours due to additional breaks and fatigue. We have applied longer shifts to the critical path and have seen overall duration reduction. We have also had mixed results with the concept of Non Stop Critical Path, also referred to as “tool to tool”. Some types of work are machine rate based, for example tasks such as pipe welding or sand blasting. For this type of work the value is in the “wrench or tool time”. The concept is that the tool never stops. The welder stays on the tool until someone comes, taps the worker on the shoulder, takes the welding rod and keeps on welding. While working spotters make sure the value adding worker never has to go searching for weld rod; an assistant keeps the worker supplied. The tool never takes a lunch break, or goes on treasure hunts; the tool works as close to 24 hours as possible. To do this we have spotters filling in for the workers when they take their breaks, and stagger crew start times. Shutdowns can have a range of % critical path work. Sometimes the critical path is almost the entire outage work scope; in other cases the critical path work can be as little as 5% of the overall outage effort. We believe that when the critical path is narrow, or a small portion of the overall work, then applying additional labor to the critical path can greatly reduce the overall cost and duration of the outage. Staffing Non Stop Critical Path of course takes more resource and is a higher operating expense then the normal 2 ten hour shifts. Non Stop Critical Path provides not only an additional 4 hours of shift time compared to 2 Tens, it also adds back two lunches, 6 breaks, and 2 sets of getting to and from the work face, or some 7 or more hours of tool time per day. The combination of shift patterns, over time, mix of critical path work, equipment rentals, etc. makes it difficult to apply a general rule for all turnarounds as to whether extending shift length or adding labor to the critical path increases or decreases overall outage expenses. So a model is needed to answer the question of under what conditions does applying extra labor to get a shorter outage actually cost less. |
|
|